B2Gold commissions mobile crusher after April fire at Goose Mine disrupts fixed plant
Bitget2026/09/28 11:03- B2Gold commissioned a new mobile crushing plant at Goose Mine in August, stabilizing ore crushing capacity following an April fire.
- Mobile crushing has averaged more than 3,000 tonnes per day since mid-August, matching plan.
- Fixed-plant repairs tied to fire damage are scheduled to finish in mid-October, targeting sustained throughput of 3,200 tonnes per day.
- The company kept 2026 Goose output guidance unchanged at 170,000 to 200,000 ounces of gold.
- Capital spending totaled about USD 16 million for the mobile plant, with USD 11 million for Phase 1 fixed-crusher upgrades.
Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.
You may also like
About 700,000 BTC have flowed out of exchanges in the past year.
Korean retail investors shift to the US in Q3: Sold over 5.5 trillion won of Korean stocks, purchased more than 10 trillion won of US stocks
In the third quarter, Korean retail investors made net purchases of US stocks worth approximately 10.15 trillion won, marking a complete reversal from the previous pattern in the first half of the year, when they made net purchases of nearly 100 trillion won in KOSPI stocks. In September alone, the sell-off amount reached as high as 14.2 trillion won. Analysts attribute this shift to a combination of factors: a sharp decline in KOSPI at high levels, the continued strength of the US stock market driven by AI themes, and the appreciation of the Korean won reducing currency exchange costs.
Copper prices approach historic highs! UBS remains bullish: "Still most optimistic"