Ferrovial targets October 2027 financial close for I-285 East Express Lanes project
Bitget2026/10/27 21:10- Ferrovial expects commercial close for Atlanta's I-285 East Express Lanes in December 2026, with financial close targeted for October 2027.
- The committed, 23-mile first phase carries $8.9 billion in construction costs, with a proposed concession payment of $23.6 billion.
- Groundbreaking is expected in the first quarter of 2028, with full service scheduled to begin in 2034.
- Two subsequent phases target openings in 2036 and 2040, respectively, under separate agreements within the development framework.
- The developer targets double-digit equity returns, expecting to fund equity commitments without issuing shares at the parent level.
Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.
You may also like
UBS Bets on Pound and Gilts: UK May Be the "Best House in a Bad Neighborhood"
UBS is optimistic about the British pound and UK bonds, describing the UK as "the best house in a bad neighborhood." The bank is betting that the Bank of England will raise interest rates less than the market expects, with the two-year yield possibly dropping to 4.5%.

Both WTI and Brent crude oil prices fell more than 1% intraday.

Nvidia plans to acquire diffusion model startup Inception for $500 million, betting on AI acceleration technology
Diffusion models are faster at generating than mainstream autoregressive models and are especially adept at producing long-form outputs. This acquisition will strengthen the Nemotron open-source model, positioning it to directly compete with OpenAI and Anthropic, and extend its capabilities into the "physical model" domain for robotics.